The final coat of polyurethane was put on the hardwood floor and stairs on Tuesday, needs 24 hours to dry before you can walk on it and 7 days for complete cure.
The appliances are delivered and should be installed on Wednesday.
We are hoping to move in Sunday 12/23 *IF* everything falls into place;
12/19 - Appliances installed, pantry finished
12/20 - Dishwasher installed and final inspection by the COunty
12/21 - Kitchen backsplash to be grouted and all slate floors and travertine to be sealed
12/22 - No activity as floors need 24+ hours to dry
Weather is for snow all week and we did get 15" on Tuesday night!